Underwater Lifting & Rotating Stage | 3 Independent Rings + DMX512 Control
POSTED: 4/27/2026
개요
프로젝트: Underwater lifting & rotating stage (3‑tier cake structure)
클라이언트: Suzhou Siyan Culture Development Co., Ltd.
Industry: Cultural tourism & performing arts
주요 과제: Underwater corrosion, 3 independent rings, DMX512 control, 30m hydraulic piping, tight access (1500×2000mm)
Suzhou Siyan Culture Development Co., Ltd. is producing a high‑end show integrating water, wind and lighting. Immersive cultural tourism is booming across China – sold‑out water shows in Wuhan, immersive performances in Suzhou (Panmen, Zhouzhuang, Lion Hill Grand Theatre). Demand for custom stage equipment is surging.
핵심 사양
| 매개변수 | 가치 |
|---|---|
| Outer ring diameter | Φ7000mm |
| Middle ring diameter | Φ4900mm |
| Inner ring diameter | Φ2800mm |
| Travel per ring | 600 / 1000 / 1500mm |
| Total load capacity | 1500kg |
| Rotation speed | 1-5 min/rev (VFD) |
| Hydraulic medium | Water‑glycol fluid |
| Corrosion protection | Galvanising + epoxy + PVC topcoat |
| Control protocol | DMX512 |
| Pump station distance | 30m |
| Site access | 1500×2000mm |
| Order→shipment | 14 days (urgent) |
솔루션
2.1 Corrosion Protection: Hot‑Dip Galvanising + Multi‑Layer Coating
접근 방식: Conventional stages have no corrosion protection. This stage operates fully submerged. Solution: hot‑dip galvanising (sacrificial anode protection) + epoxy primer + PVC topcoat.
이점: Dual protection – even if topcoat is damaged, the zinc layer continues to protect.

2.2 Eco‑Friendly Medium: Water‑Glycol Fluid
접근 방식: Hydraulic oil leaks produce oil films on water. Switched to water‑glycol fluid – transparent, no visible film. Paired with hydraulic water cylinders and water pumps.
이점: Zero water contamination, reduced maintenance, pure visual effect.

2.3 Three Independent Rings: Enhanced Choreography
접근 방식: Outer ring Φ7000mm, middle Φ4900mm, inner Φ2800mm. Each lifts separately (travel 600/1000/1500mm) and rotates independently (VFD, 1‑5 min/rev).
이점: Full creative freedom – complex motions like inner rising while outer rotating, synchronised with water, wind and lighting.

2.4 30m Remote Piping: Redundant Pre‑embedding
접근 방식: Pump station 30m from pit edge. Pipes must be embedded before stage arrives. Redundant interfaces added because fountain hole locations are not finalised.
이점: Proactive coordination avoids delays; redundancy absorbs site changes.
2.5 DMX512 Unified Control: Sync with Lighting & Fountain
접근 방식: Industry‑standard lighting protocol DMX512. Each ring has three position states (low/middle/high) and three rotation states (forward/reverse/stop), with repeat positioning.
이점: Stage motion can be choreographed like lighting cues – true water‑moves‑with‑music, stage‑rotates‑with‑light immersion.

2.6 Tight Access: Segmented On‑Site Assembly
접근 방식: Entrance only 1500×2000mm – a fully assembled Φ7000mm ring cannot enter. Solution: fabricate each ring in radial segments (each ≤1500mm wide), transport separately, weld in the pit.
이점: “Divide and conquer” – fits through narrow access, reduces on‑site lifting difficulty, modular interfaces maintain factory‑calibrated performance.